The Comptroller’s Office found that Ulster County Department of Public Works’ Bridge Crew has significantly improved bridge inventory conditions, reducing the number of poor condition bridges from 45 bridges to 34 bridges, a reduction of 24%.
The review also analyzed Bridge Crew hours from 2018 through 2025. Sixty-eight percent of hours were classified as tasks requiring specialized bridge skills, including work on non-bridge projects. Fifty-eight percent of hours were not associated with a specific project. The Comptroller’s Office recommends that DPW identify a project and assign staff time whenever possible to improve workload and resource planning.
“The improvement in bridge conditions is encouraging, and we need to build on that progress,” said Ulster County Comptroller March Gallagher. “Bridges are vital transportation links for our communities, connecting residents to work, school, emergency services and more. Washing salt from bridges and controlling brush around bridge abutments can significantly extend bridge life. We need to prioritize preventative maintenance to protect our infrastructure and save taxpayers funds.”